Headquarters construction project Neusäß – November 2022

31.10.2022 – 25.11.2022

Exterior basement walls are finished, insulation is already partially laid on the outside and part of the excavation pit is being filled in again. Additionally, the interior basement walls are being built.

The remaining exterior walls are being shaped and poured.

The outer walls are insulated.

Almost all the interior basement walls are finished. Only part of the stairwell ellipse is still missing.