Headquarters construction project Neusäß – September 2023 | Part II

01.09. – 30.09.2023

The interior work continues, the sun blinds are installed and the frame for the glass roof above the stairwell hovers in place

The sun blinds are installed

The concrete walls in the open-plan office on the 1st floor have already been primed – and ventilation ducts are being installed

Some of the ventilation ducts run under the false floor here. Hopefully the fitters know their way around this maze of ducts!

On the 2nd floor, only screed is applied to the floor, so that the ducts for the electrical installation on the floor are not allowed to be too thick. The first walls are plastered.

The square outlet boxes give you a rough idea of where desks will be located later on. You can see the blinds fitted on the outside of the windows.

Our stock storage machine is rather inconspicuous in the back corner of the warehouse.

All the concrete walls on the first floor have also already been primed.

The frames for the glass roof above the stairwell float in.

The glass panes are still missing, so the frame construction had to be wrapped again to make it weatherproof and rainproof.