Headquarters construction project Neusäß – September 2023 | Part I

04.09. – 15.09.2023

The stock storage machine is delivered and assembled

The almost 7 m long side sections of the stock storage machine have to be transported to the installation site – no easy task

A side panel up close

On the left the two side panels, on the right the “shelves”, i.e. the individual shelves

This is where the stock storage machine will be located – although this is only a view of the first floor. It will extend over two floors: basement and ground floor. This is why it has to be installed at such an early stage, as the long side sections could not be installed later.

Inserting the side panels is precision work.

Scaffolding has been erected for the rest of the assembly work – here is a view of it on the ground floor.

… and here in the basement

The stock storage machine is gradually taking shape

As construction is still ongoing, the stock storage machine first had to be wrapped up properly.