Headquarters construction project Neusäß – November 2023

01.11. – 30.11.2023

The stairwell finally has its glass roof, vast quantities of pipes and cables are still being laid and the walls are being plastered

To see the glass roof from the outside, you have to climb over the outer scaffolding up to the roof

The screed has been laid throughout the first floor. The rooms are increasingly giving an idea of what they will look like later. Here is a view of the entrance area from the inside.

And photographed from the same place towards the back in the direction of the stairwell ellipse.

View into the multifunctional room from the stairwell ellipse.

And now from the front glass wall into the room.

Heating distribution in the basement is becoming increasingly complex.

The screed has also been laid on the 2nd floor. The pipes for the heating/cooling run along the ceiling.

There is no screed on the 1st floor, as a double floor will later cover all the pipes, ducts and cables on the floor. Here too, the heating/cooling is laid in the ceiling.

The exterior was plastered and painted, just in time for the onset of winter.