Headquarters construction project Neusäß – July 2023 | Part II

03.07. – 31.07.2023

The facade is largely sealed – work on heating/cooling and ventilation system part 2

Work on the toilets has already begun

The distribution station for heating and cooling continues to expand.

The first ventilation ducts are installed in the basement.

The facade of the extension is now seamlessly and closely connected to the existing building

A lounge for the employees with its own roof terrace will be created here. Currently, the facade elements are still being sealed from the outside.

Part of the facade is still covered with protective film, but you can increasingly guess what it will look like one day.