Headquarters construction project Neusäß – June 2023 | Part II

19.06. – 30.06.2023

The construction of the facade on the 1st and 2nd floor begins – simultaneously, the installation work continues, especially in the heating area

The frame elements of the glass facade for the 1st and 2nd floors are in one piece. They are placed from above in front of the ellipses of the two floors. Here, the remaining elements are still stored in front of the support for the glass roof of the staircase.

The frame elements are not yet in their final positions.

In the meantime, the opening above the stairwell has also been provisionally covered so that rain can no longer enter.

Even through the temporary tarp still gets a lot of light into the stairwell…..

…. and you can already get an idea of how the stairwell ellipse will look later on. Lamps will be installed in the slots in the wall.

Meanwhile, work continues in the boiler room. Distribution stations are being built and pipes are being laid.